We intend to provide a weekly update on the construction progress in and around Adohi until the work has minimal impact on you. Below is the plan for the period of Aug. 19-24.
Interior of Building: The contractors will continue working this week on the interior of the building, in the lounges and public areas of the building from 8 a.m. to 5 p.m. While the goal is to limit the noise, there will be drilling, hammering and other construction-related noises.
Exterior of Building: Work on the landscaping will begin at 7 a.m., continuing until it is dark outside. Be mindful not to take shortcuts through the dirt, gravel, grass or create your own path as the ground will have unfinished areas not suitable for use. There will be noise as landscaping and rock placement continues.
Progress Plan: After Saturday, Aug. 24, we expect the remaining work to have minimal impact with work outside continuing through at least the first week of classes. Exteriors site work will have a delayed start time once classes begin. We will continue to provide weekly updates as we coordinate with our contractors.
Recent Comments